2.2.1. A detailed description of the subject of the contract
the contractor is required to complete the subject matter of the contract the method "comprehensive", at least in as described below for the following:
1. Dealing with all the necessary documents and projects, to obtain any decision on behalf of contracting and licenses required to reach a decision on environmental considerations,The building permit and other necessary for the implementation of the subject of the contract decision and licenses.
2. To implement the social communication.
3. To perform the test ground investigations in the area covered by the subject of the contract. '
4. The building project and the executive for the whole object of the contract. To obtain an opinion.The implementation of the provisions of the construction Law and related provisions of the act, up-to-date during the period of implementation of the subject of the contract.
5. The arrangements as procedural law is concerned to the extent necessary to comply with investment, including environmental studies, obtaining a decision and decision of environmental considerations, if necessary, the permit issued pursuant to DecisionDecision to permit the construction.
6. The expansion station 400/220/110 kV Pątnów in three stages.
7. The stage 1 expansion station:
(a) extension, in an existing building, distribution of 400 kV GIS two fields,
b) building connections szynoprzewodowego SF6 400 kV between field no 5 switchboards 400 kV line and 400 kV cable between Kromolice track II,
(c) the equipment and adaptive work, including project work associated with the introduction track II line 400 kV between Kromolice - Pątnów field to No. 4 400 kV switchboards in SE between Kromolice, and work relating to the verification and existing equipment running the.
8. The stage 2 expansion station:
(a) conversion and skablowanie exit line 110 kV: Janikowo, Pakość 2,Konin and mills to release construction indoor switchboards 110 kV,
b) removal of stranded between gates switchboards 110 kV and 110 kV line marginal pillars,
c) the three pillars fittings 110 kV - type posts shall be agreed with the line owners, TJ Energa S.A. and the PAK S.A. ,
(d) the construction of 110 kV cable lines to linear gate pillars fittings,
e) install stranded wires between Poles by piping and existing marginal pillars line 110 kV,
(f) expansion building nastawni,
g) power conversion needs its own station,
h) construction of a new indoor 29-field switchboards 110 kV in the 2S, in SF6 is isolation,
I) building sewer cable between the building will allocate 110 kV and building construction technology,
j) sukcesywną introductions to the new distribution facility 110 kV: distribution lines, transformers, line needs its own block, and autotransformer AT1,
k) install container for the compressor supply compressed air installation distribution 220 kV,
l) remove an existing 110 kV switchboards compressor along with the building and its own requirements.